Design Briefs

Team Design Brief: Design and produce working plans for a self sustainable waterfront property on Atlantic street in Highlands NJ, to serve as a restaurant bar and marina for tourists and Highlands locals throughout the year, to replace The Clam Hut that was destroyed in Super Storm Sandy.

Individual Design Brief: Design and produce working plans for and eco friendly marina and deck, to serve as a dock and an extension of the restaurant and bar, for tourists and Highlands locals to use throughout the year, to replace the Clam Hut dock and outside dining deck that was destroyed in Super Storm Sandy.

October 11, 2013

Weekly Log


October 4 to October 10:

 

Work Completed:

Friday October 4: Contacted Mike Danko about developmental work and a possible meeting.

Sunday October 5: Went to different marinas in Highlands to look at structures and renovations

Tuesday October 8: Consulted with group members about group site plans and drawings.

Thursday October 10: Contacted Highlands Municipal Center for site and building plans. Contacted Mr. Paul Vitale, the building officer of Highlands, regarding site plans and developmental work

Work to be Completed:

I need to finish the drawing of my site plan and work on my developmental work and keep in contact with Mr. Paul Vitale.

Issues to be Solved:

Getting the actual site plans from the Highlands Municipal Department

Communication with Mentor:

Contacted Mike Danko and Paul Vitale

Areas where help is still needed:

I need to review my new designs with Mr. Danko and Mr. Vitale to make sure they are feasible and viable.

October 4, 2013

Weekly Log


September 27 to October 3:
 
Work Completed:
Friday September 27: I finished my testing procedures and watched the video of my initial progress update and started my presentation reflection.

Saturday September 28: I finished my presentation reflection and researched the Belmar Municipal Marina.

Tuesday October 1: I edited my design brief and specs and limits.

Thursday October 3: I started the drawing of the site plan.

Work to be Completed:
I need to finish the drawing of my site plan and work on my developmental work contact mentor.

Issues to be Solved:
Further researching Belmar Municipal Marina to see the issues a floating dock marina faced.

Communication with Mentor:
I had no contact with my mentor this week.

Areas where help is still needed:
I need to review my new designs with my mentor to make sure they are feasible and viable.

September 27, 2013

Weekly Log



September 20 to September26:

Monday September 23: I finished the model and rationale report. We held a team meeting with the teachers about the direction of the project based on the models. The group realized we need to collaborate more on how everything is going to work together.

Thursday September 26: I presented my initial progress update and started the presentation evaluation. During my presentation some of my visuals failed to upload so I am finding out why that happened. My teachers brought some points to my attention regarding testing and my designs that I plan on researching further.

September 20, 2013

weekly log


Weekly Log

September 13 - September 19:

                Saturday, September 15: Group met at Chilango’s Mexican Restaurant and walked down to the Clam Hut to evaluate and document the site. Finished background information, design brief, research, and alternate solutions.

                Wednesday, September 18: Group had our first personal meeting with our shared mentor Mr. Tom Micai, for lunch. He answered some of questions regarding research and gave the group other references such as Professor Tom Harrington’s wave research. Finished group design brief.

                Thursday, September 19: Worked on models. Contacted Gateway Marina about information on utilities, but still have not heard back from them.